Progress

Sector: Water Supply
Project Name ULB Value of Works (in Rs. Cr) Name of Contractor /Agency Starting Date Completion Date Status Grade
KIUWMIP Harihara Rs 22.84 Crore M/s Seth & Sura Ltd 18-05-2017 17-11-2018 8.65% (0.06 km) Satisfactory
KIUWMIP Byadgi Rs 6.32 Crore M/s Seth & Sura Ltd 18-05-2017 17-11-2018 38.47%( 5.66 km) Satisfactory
KIUWMIP Davanagere Rs 83.37 Crore M/s Shriram EPC Ltd 01-08-2017 01-02-2020 Pipe procurement Satisfactory
KIUWMIP Byadgi Rs 38.46 M/s Shriram EPC Ltd 16-08-2017 16-08-2019 Under design validation Satisfactory
KIUWMIP Harihara Rs 58.28 Crore M/s Veolia India 01-09-2017 01-12-2019 Under design validation Satisfactory
KIUWMIP Davanagere Yet to be awarded
KIUWMIP Ranebennur Rs 135.42 Crore M/s veolia India 06-10-2017 17-11-2018 8.65% (0.06 km) Satisfactory
KMRP Chintamani Rs 1.35 Crore Sree Subha Sales 02.05.11 30.06.13 Completed Satisfactory
KMRP Chitradurga Rs 0.22 Crore M/s. Suresh Electricals, Bellary 6.04.10 30.08.11 Completed Satisfactory
KMRP Chitradurga Rs 1.73 Crore M/s.Chetas Control System 29.11.13 31.12.15 Completed Satisfactory
KMRP Hassan Rs 1.5 Crore M/s Sujala Structures, Bangalore 27.10.10 23.12.11 Completed Satisfactory
KMRP Hassan Rs 1.08 Crore M/s Sanjay B Patil, Ichalakaranji 11.08.10 31.12.11 Completed Satisfactory
KMRP Holenarsipura Rs 2.83 Crore S. Narayana Reddy 20.01.14 29.02.16 Completed Satisfactory
KMRP Sira Rs 0.69 Crore Sri.Ravindrakumar.M. Class-1 Contractor 27.04.12 13.05.13 Completed Satisfactory
KMRP Jevargi Rs 0.71 Crore Mr Golayya.C Hiremath 17.11.11 20.08.13 Completed Satisfactory
KMRP Jevargi Rs 0.52 Crore Mr Golayya.C Hiremath 06.02.14 30.11.14 Completed Satisfactory
KMRP Chikmagalur Rs 2.79 Crore V.Narasimhan, Class I Contractor, Bhadravathi 10.12.12 31.1.17 Work terminated, Work being taken under AMRUT Un-satisfactory
KMRP Savanur Rs 0.49 Crore S.K.Thangal 29.03.11 26.09.11 Completed Satisfactory
KMRP Haliyal Rs 2.12 Crore M/s Praveen Electricals, Gadag 18.09.15 29.02.16 Completed Satisfactory
KMRP Haliyal Rs 11.37 Crore M/s. Jain Irrigation System Ltd 14.02.14 31.05.17 Completed Satisfactory
KMRP Madikeri Rs 0.9 Crore V.Nagaraj, Mysore 19.02.09 14.07.10 Completed Satisfactory
KMRP Nanjungud Rs 28.56 Crore M/s. Pragathi Construction & Shradha (JV) 26.02.14 31.12.17 Work under Progress
KMRP Magadi Rs 20.4 Crore M/s. Viswaraj Environmental Pvt Ltd Nagpur 04.04.14 31.12.17 Work under Progress